Study, Design, Improvement, Construction, Operation & Maintenance of Irrigation at Al-Abdali Farms
Project: Study, Design, Improvement, Construction, Operation & Maintenance of Irrigation at Al-Abdali Farms.
Role: Main Contractor
Client: Ministry of Public Works
Status: ongoing
Replacing Fresh Water Pipeline 40” Dia & Ductile Iron Pipeline 1000mm Dia with a 1200mm Dia Ductile Iron Pipeline from Doha Pumping Station to Mutlaa Reservoir area
Project: Replacing Fresh Water Pipeline 40 Dia & Ductile Iron Pipeline 1000mm Dia with a 1200mm Dia Ductile Iron Pipeline from Doha Pumping Station to Mutlaa Reservoir area.
Role: Main Contractor
Client: Ministry of Electricity & Water
Status: ongoing
Installation and Relocation of Pipelines and other services for Jamal Abdul Nasser Street
Project: Installation and Relocation of Pipelines and other services for Jamal Abdul Nasser Street
Role: Subcontractor
Client: Ministry of Public Works
Status: ongoing
Periodical Maintenance & Installation of Fire Hydrants All Over Kuwait
Project: Periodical Maintenance & Installation of Fire Hydrants All Over Kuwait.
Role: Main Contractor
Client: Ministry of Electricity & Water
Completion: 2012
Construction of 282 Housing units, Public buildings and Main Infrastructure Works
at Saad Al Abdullah residential neighborhood
Project: Installation, Construction & Maintenance of1200mm diameter ductile iron distribution pipeline from West Jleeb Alshioukh Water Towers to 6th Ring Road with Pipeline 600mm Dia.
Role: Main Contractor
Client: Ministry of Public Works
Scope of work: Installation of ductile pipe 1200mm diameter with 10Km long connection with West Jleeb towers including trenchless pipe jacking under crossing roads.
Completion: 2008
Construction of 282 Housing units, Public buildings and Main Infrastructure Works
at Saad Al Abdullah residential neighborhood
Project: Replacing Existing Fresh & Brackish Waster Asbestos Cement Pipes with Ductile Iron Pipes at Ahmadi
Role: Main Contractor
Client: Ministry of Electricity & Water
Completion: 2011